The Helix
The Helix project was begun in early March, 2013 and
was the most complex project we undertook since construction of the layout began. We
removed the last ten feet of our layout and replaced it with new construction
extending out twenty feet. The new area contains our Helix which
connects our layout's lower and upper levels. Although we have always had
a connection between the two levels it was mostly on hidden track work and our members rarely used it,
mainly because they lost sight of their train for the several minutes it took to traverse
between levels. The new Helix is exposed and significantly shorter, and
therefore will be operationally more "user-friendly."
Enjoy the photos below and follow the work as it was being done.
|
Here a photo of members Robby Kransteuber (left) and Jack Shelly
discussing plans for the Helix. The area outlined with the masking
tape on the floor will be the location of the new Helix. |
|
This is a mockup of the construction technique
used on the Helix. Since the lower level consists of two separate main
lines the Helix was designed for two track side-by-side mainlines, one to carry trains from lower to upper
level, and the other from upper to the lower level. |
|
This was the first day of our project. We were in the middle of
removing this entire corner of our layout. A lot of work went into building
this area, and although we salvaged what we could for re-use, it was
still quite sad to tear it down and throw it into the trash.
But, that's progress! |
|
One of the bridges from this section being removed. We had three bridges
in this area and we
saved them all for re-use elsewhere. |
|
A heap of trash from what used to be a beautiful section of our
layout. There's was no turning back at this point! ONWARD! |
|
Demolition is just about complete. The 110 volt wiring had to be
removed in addition to some of the layout wiring. Next we did a little
sweeping, some clean up, and then we started laying out the new construction. |
|
Here's a photo of some of our crew hard at work. I believe someone
needs to have a talk with the foreman in charge. |
|
After the old bench work was cut away we cut an access hole which
leads to the basement. This ended up being in the middle of our Helix
and allowed us to access any problems that might occur during the travel
of trains on the Helix. |
|
Prep work is finished and member Robby Kransteuber is starting the supports for
the risers. Obviously some of the other members of the club believe he
requires some supervision. |
|
April 03, 2013 - The risers being installed. Thank goodness we had enough
supervisors for this project. |
|
April 8, 2013 - This is an example of the construction
method we used for the sub roadbed. It took a lot of planning but
construction moved along quickly and yielded a strong base for our track
work. And, there was minimal waste of materials with this
construction method. |
|
A test fit using a plastic spline to see how the roadbed was going to
form the curve. With this method of construction a smooth curve is
automatically formed. |
|
May 5, 2013 - The first of the track being laid by
member Tony Matukonis. If you look closely you can see the tie-in of the lower
track to the existing layout. The track work Tony is installing will be
a simple loop track for our lower level. The Helix roadbed has not
yet been installed. We used code 100 flex for the hidden track and
blackened code 83 for the upper level. Also, we installed an
electrical feeder for each three foot track section to ensure reliable
electrical continuity. |
|
July 03, 2013 - We've installed electrical outlets around the entire
Helix. This makes it a lot easier to use our power tools, solder
guns, etc. |
|
July 10,2013 - John Wiegand wrapping it up for the night. At this
point we had
about half the Helix completed with two more layer to go. A lot of the top
portion of the framework will be removed after we determine the final
height. |
|
August 15, 2013 - At this point the Helix is just about completed but we still had
the run around track to install. Electrical track feeders are installed for the
most part. |
|
Sept 05, 2013 - Just about all the main track work had been installed. The
Helix is complete along with the main line run around track. We still needed
to install the track at the top of the Helix to serve the industries and
the necessary scenery and structures to go with it. This last area had
not yet been decided upon as we had not yet come up with an agreed-upon
landscape for this section. |
|
July, 2014 - Yard track work is nearing completion. Scenery, buildings
and other items are not yet decided upon and will be installed as we
acquire them. |
|
August, 2014 - A small bridge over a creek being checked for fit
and will be permanently installed as soon as the "river" is poured. |
|
Sep, 2014 - Other bridges were placed and awaited the
completion of the yet-to-be-poured "river." |